We are excited to get started with building the Surf City Municipal Complex! Over the last few weeks, we have been busy at work with the following tasks. 

Construction Update (past two weeks):

  • Passed proof roll and continued site fill - 90% complete (over 10,000 yards)
  • Continued pond excavation and construction
  • Installed rip rap weir in pond
  • Storm drainage structures and piping were delivered
  • Verified existing waterline and sanitary sewer elevations
  • Completed PME underground coordination drawings
  • Mobile field office was delivered
  • Pro-installation meeting for utilities

Next two weeks:

  • Complete site fill and compaction
  • Complete building pad prep
  • Begin installation of storm drainage & sanitary sewer system
  • Begin installation of fire & domestic water piping, back-flows, & meters
  • Rebar delivery (7/28)
  • Begin prep, layout, and excavation for footings
  • Begin rebar install & concrete placement
  • Begin layout, excavation & install of plumbing & electrical undergrounds
  • Begin layout & install of CMU foundation block
  • Pre-Installation meetings for underground electrical & plumbing

Underground Utility Layout

Underground Utility Layout 1

Underground Utility Layout

Underground Utility Layout 2